Source: BUS Rheinland-PfalzA building may only be used once it has been properly completed and is safe to use.
In the case of structures requiring approval and structures for which the exemption procedure has been carried out in accordance with Section 67 of the Rhineland-Palatinate State Building Regulations (LBauO), the date of final completion must be notified to the lower building supervisory authority (notification of completion).
The building may be used at the earliest one week after the date stated in the notification of completion.
Upon application, the building supervisory authority should allow the building to be used earlier in whole or in part if there are no concerns about public safety or order.
When constructing or modifying combustion systems, the building owner must have the authorized district chimney sweep certify the safe usability of the flue gas systems and the connections of the fireplaces before commissioning.