mixins.searchInfo_searchTermApplying for an extension of a final operating plan for mining

Applying for an extension of a final operating plan for mining

Source: BUS Rheinland-Pfalz

You need an approved operating plan in order to be able to carry out the measures for discontinuing a mining operation. An operating plan is used to monitor operations. It generally includes comprehensive explanations and planning documents for planned mining measures, for example with regard to

  • Location and extent,
  • technical implementation
  • scheduling,
  • possible effects on people and the environment,
  • measures to avoid and minimize negative effects on the environment,
  • operational and occupational safety.

If you wish to discontinue your mining activities in the entire operation or only part of the operation, for example because the raw material deposits have been exhausted, you must draw up a final or partial final operating plan. Once the work has been carried out and the official approval has been granted, mining supervision for the operation or part of the operation is terminated. This final or partial final operating plan must be approved by the competent authority.

If you wish to extend this final or partial final operating plan, you must also apply for approval.

The final or partial final operating plan regulates the measures that you will carry out after the actual extraction or exploration operation has ceased. In particular, you must explain how you will ensure that the cessation of your operations has no negative impact on people or the environment and that the surface can be reused. This means that your final operating plan must contain the following information, among other things:

  • Precise description of the technical measures and facilities as well as details of the economic operating conditions,
  • Duration of the measures,
  • reasons for the closure,
  • Mine layout or graphic representation of the operation,
  • Information on the mineral resources extracted and their intended use,
  • information on the disposal of waste produced, operational plant and equipment or their use for other purposes,
  • Chemical analyses,
  • descriptions of the geology of the deposits,
  • operating history, if applicable.

No environmental impact assessments (EIA) are required for the approval of the extension of your final operating plan.