Ensuring operational safety - apply for a permit to erect and operate installations with pressure equipment
Source: BUS Rheinland-PfalzFilling systems with pressure equipment in which transportable pressure equipment is filled with a filling capacity of more than 10 kilograms per hour for delivery to others are systems requiring monitoring.
You will need a permit from the relevant authority if you are using a filling system:
- want to build and put into operation, or
- want to change the design or mode of operation in such a way that the safety of the system is affected.
Permission can be granted to you subject to the following restrictions:
- limited
- temporary
- under conditions, or
- with conditions.
If the installation requiring a permit is part of an installation requiring a permit, no separate permit will be issued. The permit includes the permission.